Friday, August 10, 2007

This is the framing that was done last Friday- Saturday&Monday. Yes it took the men 3 full days to frame what would take anybody else 1 day to do and even then I had to have a man come in and put 68 screws in the studs because they weren't screwed off right. The guys in the back ground are Plumbers they were roughing in the pipes they failed their inspection again so they are 2 for 2 where do these people come from??? I had 3 inspections plumbers failed electrical failed and the only reason that the framing passed is because I made a man come in and add screws otherwise I would of been 3 for 3 as it is I have only passed 2 out of 6 that tells you something about the people in Charlotte NC. I can see why the inspectors are the way they are.